Uinta Basin Replacement Project
Big Sand Wash Reservoir Enlargement

The Central Utah Water Conservancy District is seeking contractor services for the construction of the Uinta Basin Replacement Project, Big Sand Wash Reservoir Enlargement to be constructed for the District as part of the completion of the Central Utah Project. The project is located in Duchesne County, Utah and will consist of completing the Dam raise by either an earthen dam/clay core option, or an earthen dam/slurry wall option. Field construction work is expected to begin in March 2004 and is to be completed by November 30, 2005.

A prequalification packet may be obtained by contacting Katherine Crenshaw at 801.226.7123. Questions regarding the project should be directed to Mr. Kirk Beecher, P.E., Project Manager at 801.226.7193.

A PDF of this notice can be downloaded here.

 

Tentative Project Schedule
Prequalification Statement available at the District for pickup by prospective contractors
Friday, August 29, 2003
Mandatory pre-bid conference and site visit
(only contractors who attend this conference will be allowed to bid)
Thursday, September 18, 2003
Prequalification Statement due at the District
Tuesday, September 23, 2003
at 4:00 pm
Notification of pre-qualified contractors
Friday, October 3, 2003
95% Contract Documents available
Friday, October 3, 2003
Contract Documents available
Tuesday, October 17, 2003
Bid Opening
Wednesday, November 5, 2003
Award Date
Wednesday, November 19, 2003
Notice to Proceed
Tuesday, January 6, 2004
Pre-construction meeting
Tuesday, January 6, 2004
Start Field Construction
Monday, March 1, 2004
Construction Completion
Tuesday, November 30, 2005