diamond fork pipeline project summary
|
The Diamond Fork Pipeline and Road Rehabilitation Project is located in Utah County, Utah. The construction site extends approximately 7.2 miles up from the mouth of Diamond Fork Canyon and is accessed from US Hwy #6 in Spanish Fork Canyon.
The project consists of construction of approximately 7.2 miles of 96" diameter welded steel pipe from the Monks Hollow area to the confluence of Diamond Fork Creek and the Spanish Fork River; and reconstruction of the existing Diamond Fork Road along the pipeline alignment.
The Strawberry Tunnel was constructed as part of the Strawberry Valley Project and has historically been used to deliver SVP water to the Bonneville Basin. Syar Tunnel and Sixth Water Aqueduct are currently used for the transbasin diversion of SVP water from Strawberry Reservoir. The use of Strawberry Tunnel is limited to releases for streamflow maintenance except that irrigation water may be conveyed under special circumstances.
Substantially Complete Notice
November 26, 1997 the Diamond Fork Pipeline was found to be substantially complete
The notice read as follows:
November 26, 1997
Subject: Diamond Fork Pipeline and Road Rehabilitation Project Finding of Substantial Completion
After completion of an on-site field inspection, and upon the joint recommendation of Curt Pledger, Resident Engineer; Wayne Miller, Chief Inspector; Sheldon Talbot, Project Manager; and Lee Swenson, Environmental Programs Office; I find the Diamond Fork Pipeline and Road Rehabilitation Project (contract C-1) to be substantially complete as of November 26, 1997.
H. Lee Wimmer, P.E.
CUPCA Construction Manager
General Project Data
| Design Engineer:
|
Boyle Engineering Corporation
|
| General Contractor:
|
PCL Civil Constructors, Inc.
|
| Construction Manager:
|
H. Lee Wimmer, P.E. CUWCD
|
| Construction Inspection Services:
|
U.S. Bureau of Reclamation
|
| Resident Engineer:
|
Curt Pledger, P.E.
|
|
|
|
| Notice to Proceed:
|
10-November-1995
|
| Original Contract Time:
|
915 Consecutive Calendar Days
|
| Original Contract Completion Date:
|
23-May-1998
|
|
|