The Upper Diamond Fork
Project was constructed for the Central Utah Water Conservancy
District (CUWCD) as part of the completion of the Central Utah Project
Completion Act (CUPCA). The Project is located in Utah County, Utah and
conveys water approximately six miles from the Sixth Water
Aqueduct to the Diamond Fork Pipeline located in Diamond Fork Canyon,
approximately 7 miles from US Highway 6/89 in Spanish Fork Canyon.
Initially the Upper Diamond Fork Project incorporated both tunnel and
pipeline segments connecting the Sixth Water Aqueduct with a to-be-built
flow control structure in the Monks Hollow area. This proposal was reviewed
by a Value Engineering team who determined that a single tunnel structure
would cost less to build and would have a lower operation cost over the
project life-cycle. This option, named "VE Design/Build Tunnel Option
T3/T10", was presented to the contractors bidding the project.
Not only does the VE "Design/Build" T3/T10 tunnel option cost less to
construct, it also will have less of an impact on the environment. This
reduced impact is outlined in the Environmental Assessment document prepared
by the Central Utah Water Conservancy District.
On January 4, 2002 the TBM mining process came to a halt when a segment
of tunnel wall caved and H2S gas levels reach nearly 400ppm in the air
(over 60ppm in the water). In the days following both the District and
the Contractor agreed it was no longer safe to continue mining along the
proposed alignment. The District developed a new plan to finish the system
by incorporating parts of the original tunnel/pipeline concept and re-bid
the remainder of the project as Phase II. Details on the concept and bidding
summary can be found in the project library.
(Bid related documents canbe found under the Miscellaneous Documents -
'Other' drop-down box, and Maps of the project can be found under the
'Map' drop-down box)
Hole-Thru Information
The Diamond Fork System was dedicated on July 1, 2004. Governor Olene S. Walker, Congressman Chris Cannon, and others contributed their remarks at the ceremony marking the completion of the project.
|