Spanish Fork River Flow Control Structure - Progress
Construction activities continue on the structures.
The Pre-Construction meeting was held July 7, 2000, and a Notice to Proceed was issued that day. Field Construction has not begun.
Bids were opened this morning at 10:00am in the CUWCD Board Room. Results are available - Gerber Construction Inc. was the low bidder.
The Bid Opening has been moved to June 27, 2000 at 10:00am
A list of pre-qualified bidders was published.
A general information meeting was held May 11, 2000 during which a brief overview of the project was given as well as a guided site tour.
Attendance was taken at the meeting
A presentation was given
|
|