Spanish Fork River Flow Control Structure - Progress

December, 2000 - Update
  •   Construction activities continue on the structures.


  • July 31, 2000 - Update
  •   The Pre-Construction meeting was held July 7, 2000, and a Notice to Proceed was issued that day. Field Construction has not begun.


  • June 27, 2000 - Bid Opening
  •   Bids were opened this morning at 10:00am in the CUWCD Board Room. Results are available - Gerber Construction Inc. was the low bidder.


  • June 19, 2000 - Notice of Date Change
  •   The Bid Opening has been moved to June 27, 2000 at 10:00am


  • May 22, 2000 - Pre-qualified bidders
  •   A list of pre-qualified bidders was published.


  • May 11, 2000 - Pre-bid conference and site visit
    A general information meeting was held May 11, 2000 during which a brief overview of the project was given as well as a guided site tour.


  •   Attendance was taken at the meeting